Location
Artvin
Type
Hydroelectric
Installed Capacity
245 MW
Year of Commissioning
2014
Arkun HEPP, which we commissioned in the second quarter of 2014, is located on the Çoruh River on the Erzurum - Artvin provincial border. Our power plant, consisting of 3 main power plants with a capacity of 78 MW and 2 environmental flow power plants with a capacity of 5,4 MW, and a total installed capacity of 245 MW, is the project with the longest energy tunnel among Enerjisa Üretim projects with its 14 km energy tunnel. The annual average energy generation capacity of our power plant is 780.1 GWh.
Alanbaşı köyü Hav Bağlığı mevkii 08800 Yusufeli/Artvin